Newly refurbished linkspan deck being lifted in place at Kennacraig

Newly refurbished linkspan deck being lifted in place at Kennacraig

Kennacraig and Port Askaig reach significant milestones in preparation for new Islay vessels

PortA programme of CMAL-led preparatory work to upgrade two ferry terminals on the Islay route has reached key milestones, paving the way for delivery of new vessels by the end of the year. Upgrades to the south berth of Kennacraig ferry terminal are now complete, while Port Askaig ferry terminal fendering work has also finished, following a six-week closure, allowing ferry services to resume.

The CMAL-led project team of contractors George Leslie Ltd, Napier Bros Engineers and Malin Group, and engineering consultants, Mott MacDonald, have installed vital infrastructure upgrades at both Kennacraig and Port Askaig to accommodate the new Islay vessels - ISLE OF ISLAY and LOCH INDAAL.

Throughout the closure, CalMac operated amended timetables for the Kennacraig – Port Ellen – Port Askaig and Oban – Colonsay – Port Askaig services to support travellers and communities on Islay, Jura and Colonsay.

Preparatory work began in November 2023 at Kennacraig, which included modification of the fixed ramp on the north berth. In January 2024, the south berth was closed to replace existing fenders, build of new piled walls, undertake dredging and remove and refurbish the linkspan. During this time, all ferry services were operating from the north berth.

After being removed for refurbishment, the linkspan has now been reinstated and is ready for ferry services to resume, with the project completed two weeks ahead of schedule. Services will now operate on the south berth, while works on the north berth, including wall construction, fender replacement, re-profiling of the fixed ramp and dredging works commence.

At Port Askaig, work began in March this year with the replacement of the existing fenders, installation of piles and concrete foundations for a mooring aid, and additional electrical upgrades. The fendering work was carried out between ferry arrivals and departures causing no disruptions to services. In June, a six-week full port closure was implemented to replace the fenders on the roundhead structure and after successful installation of these fenders, Port Askaig was reopened on 31 July as scheduled. The ongoing mooring aid foundation and electrical works will continue without any disruption to services.

© Shippax

New Islay Vessel Enabling Works (NIVEW) at Port Askaig

New Islay Vessel Enabling Works (NIVEW) at Port Askaig

Aug 09 2024


Get the latest news - for FREE

Receive our weekly newsletter with the latest news and unique special offers.

Products

Shippax Info

Our monthly magazine + Online Access.1 year subscription.

More

Shippax Market 24

Market reports & outlook

More

Shippax Guide 24

GREEN TECHNOLOGIES

More

Shippax Designs 23

FINNSIRIUS

More

Shippax Database - Single user

Shippax Database online

More

Ferry Statistics

Price upon request

More

Don’t miss out!

The place to meet the ferry shipping industry!